TOC DataCenter - PE Router Software Upgrade from 2026-06-17 21:00 EDT to 2026-06-17 23:59 EDT

Scheduled maintenance Internet VCU Campus Network VCU Wireless Network VPN (RamsVPN)
2026-06-17 21:00 EDT · 2 hours, 59 minutes

Updates

Scheduled

As part of planned infrastructure maintenance, the Network Services team will perform a software upgrade on the active Provider Edge router located at the TOC Data Center. Prior to the upgrade, all active services will be migrated to the Harris Hall Data Center PE router to minimize impact.
Two short interruptions are anticipated during this maintenance window: the first occurring during the initial service failover, and the second when services are returned to the TOC Data Center PE router following upgrade completion. Each interruption is expected to last no longer than 30 seconds.

June 15, 2026 · 13:43 EDT

← Back